Structural engineer’s mock-up of the timbrel arch...
Oct 30th
The site as of Sunday 28th October 14.00 - bungalow...
Oct 30th

Bungalow demolition

South Kent Plant & Demolition have done a superb job.  The bungalow might as well have never...
Oct 30th
From rustic to rubble in 20 minutes
Oct 30th
The bungalow timber frame disposal
Oct 30th
The aftermath.  A very large and very hot fire, which we...
Oct 30th
Warch Watch
chimney stack demolition
Oct 30th
Warch Watch
Bungalow demolition 10 minutes in.  Bye bye front door !
Oct 30th
Warch Watch
Demolition of the bungalow begins
Oct 30th
Vault tiles The first batch of tiles being made with...
Oct 23rd
Bungalow demolition  after the asbestos strip out
Oct 23rd

Bye Bye Asbestos

Following another good day’s work by the demolition contractor the bungalow is now free of...
Oct 23rd

Ecological survey complete

Following a records survey, site scoping survey and subsequent bat survey (revealing that we...
Oct 17th

Bungalow demolition

The bulldozer will be present on Friday 26th October.  By then all the asbestos will have been...
Oct 17th

Demolition begins

Demolition works start today with the stripping out of the internal asbestos panelling.
Oct 17th

WE HAVE POWER !

EDF have finally disconnected the bungalow and moved the meter to provide us with electricity in the...
Oct 17th
HawkesArchitecture.co.uk
Oct 12th

Electricity in the caravan

EDF have finally decided when they’ll come and connect the electricity to the caravan....
Oct 4th
Ecoplay greywater recycling system
Oct 1st